Main Street Reconstruction / Columbia Ave to Hart Ditch
Condemning Authority: Town of Munster, Indiana
Project Location
Main Street in Munster, Indiana
- Columbia Avenue to Hart Ditch
- Hart Ditch to Highland
Project Background and Purpose:
The Town’s vision for the Main Street Reconstruction Project includes new pavement, stormwater management, accommodations for pedestrians and bicyclists, decorative street lights, median islands, to begin construction in Fiscal Year 2025. The project will be split into two phases: Columbia to Hart Ditch first, and later Hart Ditch to Highland.
Project Description
Redesign and reconstruction of Main Street, including adding a multi-use path and/or sidewalks and bike lanes along this corridor.
Project Status
Columbia to Hart Ditch:
- Environmental Study: complete June 2024
- Tracings: complete July 2024
- Letting: complete November 2024
- Proceed to Contractor: December 2024
If you have questions or concerns regarding this project and an eminent domain taking, please contact an Indiana Property Rights attorney today.