SR 47 Improvements

 

Condemning Authority: INDOT

Project Location
SR 47 from Hamilton/Boone County Line to just west of Arrow St.

Project Description
This project is proposed to include the following improvements:

  • Resurface SR 47 from Hamilton/Boone County Line to just west of Arrow St., adding 4 ft paved shoulders.

  • Fully Reconstruct SR 47 from just west of Arrow Street through the SR 38 intersection. Add curb and gutter drainage system and a 5-6ft sidewalk along the south side of SR 47.

  • Build a roundabout at SR 47 & SR 38 intersection

  • Realign Mule Barn Rd with California Street

  • Add midblock crossings for pedestrian crossings of SR 47

  • Add enhanced Monon Trail crossing at SR 47

Project Background & Purpose
The need for this project is due to the lack or drainage and poor condition of the existing pavement. The purpose of this project is to create an effective drainage system and restore rideability of the roadway.

Project Status
This project is currently finalizing the Environmental Phase as well as the R/W Acquisition Phase. Next steps are:

  • Letting/Project Bids: 2024

  • Utility relocation: 2024-2025

  • Construction: 2025-2026.

If you have questions or concerns regarding this project and an eminent domain taking, please contact an Indiana Property Rights attorney today.

Additional Resources

Relevant Website

 
Previous
Previous

US 20 Widening

Next
Next

US 30 Corridor / Flaugh Road